Item Coversheet

Mountain View Whisman School District

Agenda Item for Board Meeting of 6/15/2017



Agenda Category:  CONSENT AGENDA

Agenda Item Title:  Stevenson/Theuerkauf/Preschool/District Office Project Phase 1 Change Order #1

Estimated Time: 

Person Responsible:  Dr. Robert Clark, Associate Superintendent/Chief Business Officer



Background: 

During the Stevenson/Theuerkauf/Preschool/District Office Project Phase 1, unforeseen conditions, design changes, and owner requests have occurred, resulting in additions/changes in scope to the original project. These additions/changes require contingency money to be used. The contingency monies required for Change Order #1 will not exceed $2,635.00. A summary of Change Order No. 1 is attached.



Fiscal Implication:

Change Order No. 1 for $2,635 is 4.5% of the contract value.  To date, 50% of the project is complete.



Recommended Action: 
That the Board of Trustees approve the Stevenson/Theuerkauf/Preschool/ District Office Project Change Order #1, as presented.

ATTACHMENTS:
DescriptionTypeUpload Date
Stevenson/Theuerkauf/Preschool/District Office Project Change Order #1 15June2017Backup Material6/9/2017