Item Coversheet

Mountain View Whisman School District

Agenda Item for Board Meeting of 6/15/2017



Agenda Category:  CONSENT AGENDA

Agenda Item Title:  Castro/Mistral Construction Phase 1 Change Order #2

Estimated Time: 

Person Responsible:  Dr. Robert Clark, Associate Superintendent/Chief Business Officer



Background: 

During the Castro/Mistral Elementary School Phase 1 – Demolition and Temporary Housing Project – Site Package, unforeseen conditions, design changes, and owner requests have occurred, resulting in additions/changes in scope to the original project. These additions/changes require contingency money to be used. The contingency monies required for Change Order #2 will not exceed $1,944.



Fiscal Implication:

The total construction contingency of $46,545 was budgeted for this project.

Change Order #1 for $70,349 utilized all contingency monies plus an additional $24,804.  Change Order # 2 will utilize an additional $1,944 with 100% of the project complete.



Recommended Action: 

That the Board of Trustees approve the Castro/Mistral Elementary School Phase 1 Change Order #2.