Item Coversheet

Mountain View Whisman School District

Agenda Item for Board Meeting of 5/21/2020



Agenda Category:  CONSENT AGENDA

Agenda Item Title:  Landels Play Structure - Change Order 1 - Terramark

Estimated Time: 

Person Responsible:  Rebecca Westover, Ed.D., Chief Business Officer



Background: 

During the Landels Play Structure Grant Project unforeseen conditions, design changes, and owner requests have occurred, resulting in additions/changes in scope to the original project. These additions/changes require contingency money to be used.

 

The total construction contingency of $42,440.00 was budgeted for this project.

 

Change Order #1 for $25,426.71 will leave the remaining contingency amount at $22,013.29 with 75% of the project complete. 

Fiscal Implication:

The contingency monies required for Change Order #1 will not exceed $25,426.71. A summary of Change Order #1 is attached.



Recommended Action: 
It is recommended the Board of Trustees approve Change Order #1 for the Landels Play Structure Grant Project .

ATTACHMENTS:
DescriptionTypeUpload Date
Landels Playstructure-Terramark - Change Order 1Backup Material5/15/2020