Mountain View Whisman School District
Agenda Item for Board Meeting of 10/4/2018
Agenda Category: CONSENT AGENDA
Agenda Item Title: Stevenson Elementary School, Phase 2, Increment 2, Electrical and Low Voltage Project Change Order No. 3 – Vanden Bos Electric
Estimated Time:
Person Responsible: Robert Clark, Ed.D., Chief Business Officer
Background:
During the Stevenson Elementary school, Phase 2, Increment 2, Electrical and Low Voltage Project, unforeseen conditions, design changes, and owner requests have occurred, resulting in additions/changes in scope to the original project. These additions/changes require contingency money to be used.
The total construction contingency of $90,980 was budgeted for this project.
Change Order #1 for $55,520 was approved on May 3, 2018.
Change Order #2 for $23,434 was approved on September 6, 2018.
Change Order #3 for $11,104 will reduce the remaining contingency amount to $922 with 100% of the project complete.
Fiscal Implication:
The contingency monies required for Change Order #3 will not exceed $11,104.00. A summary of Change Order #3 is attached.
Recommended Action:
That the Board of Trustees approve Change Order #3 for the Stevenson Elementary school, Phase 2, Increment 2, Electrical and Low Voltage Project.
|