Item Coversheet

Mountain View Whisman School District

Agenda Item for Board Meeting of 9/6/2018



Agenda Category:  CONSENT AGENDA

Agenda Item Title:  Stevenson Elementary School Project, Phase 2, Increment 1 Sitework Project Change Order No. 3 – Galeb Paving

Estimated Time: 

Person Responsible:  Robert Clark, Ed.D., Chief Business Officer



Background: 

During the Stevenson Elementary School Project, Phase 2, Increment 1 Sitework Project, unforeseen conditions, design changes, and owner requests have occurred, resulting in additions/changes in scope to the original project. These additions/changes require contingency money to be used. The contingency monies required for Change Order #3 will not exceed $15,573.00. A summary of Change Order #3 is attached.



Fiscal Implication:

The total construction contingency of $370,200 was budgeted for this project.

 

Change Order #3 for $15,573 will reduce the remaining contingency amount to $19,908 with 90% of the project complete.

 



Recommended Action: 
That the Board of Trustees approve Change Order #3 for the Stevenson Elementary School Project, Phase 2, Increment 1 Sitework Project.

ATTACHMENTS:
DescriptionTypeUpload Date
Stevenson Increment Sitework Change Order 3Backup Material8/27/2018