Agenda Item Title: Stevenson Elementary School Project, Phase 2, Increment 1 Sitework Project Change Order No. 3 – Galeb Paving
Estimated Time:
Person Responsible: Robert Clark, Ed.D., Chief Business Officer
Background:
During the Stevenson Elementary School Project, Phase 2, Increment 1 Sitework Project, unforeseen conditions, design changes, and owner requests have occurred, resulting in additions/changes in scope to the original project. These additions/changes require contingency money to be used. The contingency monies required for Change Order #3 will not exceed $15,573.00. A summary of Change Order #3 is attached.
Fiscal Implication:
The total construction contingency of $370,200 was budgeted for this project.
Change Order #3 for $15,573 will reduce the remaining contingency amount to $19,908 with 90% of the project complete.