Mountain View Whisman School District
Agenda Item for Board Meeting of 9/6/2018
Agenda Category: CONSENT AGENDA
Agenda Item Title: Demolition and Abatement for Construction of New District Office Change Order #1 – Premier Builders, Inc.
Estimated Time:
Person Responsible: Dr. Robert Clark, Ed.D., Chief Business Officer
Background:
During the Demolition and Abatement for Construction of the New District Office Project, unforeseen conditions, design changes, and owner requests have occurred, resulting in additions/changes in scope to the original project. These additions/changes require contingency money to be used. The contingency monies required for Change Order #1 will not exceed $12,420.00. A summary of Change Order #1 is attached.
Fiscal Implication:
The total construction contingency of $25,762 was budgeted for this project.
Change Order #1 for $12,420 will reduce the remaining contingency amount to $13,342 with 100% of the project complete.
Recommended Action: That the Board of Trustees approve Change Order #1 for the Demolition and Abatement for New Construction Project of the District Office.
|