Mountain View Whisman School District
Agenda Item for Board Meeting of 9/6/2018
Agenda Category: CONSENT AGENDA
Agenda Item Title: Stevenson Elementary School Phase 2, Increment 2 Electrical and Low Voltage Project Change Order No. 2 – Vanden Bos Electric
Estimated Time:
Person Responsible: Robert Clark, Ed.D., Chief Business Officer
Background:
During the Stevenson Elementary School Phase 2, Increment 2 Electrical and Low Voltage Project, unforeseen conditions, design changes, and owner requests have occurred, resulting in additions/changes in scope to the original project. These additions/changes require contingency money to be used. The contingency monies required for Change Order #2 will not exceed $23,434.00. A summary of Change Order #2 is attached.
Fiscal Implication:
The total construction contingency of $90,980 was budgeted for this project.
Change Order #1 - $55,520
Change Order #2 - $23,434
Total Change Orders to Date - $78,954
Contingency balance remaining is $12,026, with 92% of the project complete.
Recommended Action: That the Board of Trustees approve Change Order #2 for the Stevenson Elementary School Phase 2, Increment 2 Electrical and Low Voltage Project.
|