Mountain View Whisman School District
Agenda Item for Board Meeting of 4/5/2018
Agenda Category: CONSENT AGENDA
Agenda Item Title: Stevenson Elementary School Modular Building Project, Phase 2, Increment 2 Change Order No. 2 – American Modular Systems
Estimated Time:
Person Responsible: Robert Clark, Ed.D., Chief Business Officer
Background:
During the Stevenson Elementary School Modular Building, Phase 2, Increment 2, project unforeseen conditions, design changes, and owner requests have occurred, resulting in additions/changes in scope to the original project. These additions/changes require contingency money to be used. The contingency monies required for Change Order #2 will not exceed $296,385. A summary of Change Order #2 is attached.
Fiscal Implication:
The total construction contingency of $583,600 was budgeted for this project.
Change Order #1 for $242,512 was approved on August 17, 2017.
Change Order #2 for $296,385 will reduce the remaining contingency amount to $44,703, with 50% of the project complete.
Recommended Action:
That the Board of Trustees approve Change Order #2 for the Stevenson Elementary School Modular Building, Phase 2, Increment 2 Project in the amount of $296,385.
|