Mountain View Whisman School District
Agenda Item for Board Meeting of 4/5/2018
Agenda Category: REVIEW AND ACTION
Agenda Item Title: Construction Contract Award for Graham Middle School Modernization Phase 4: Courtyard (5 minutes)
Estimated Time:
Person Responsible: Robert Clark, Ed.D., Chief Business Officer
Background:
The Board will consider for award a contract for the Graham Middle School Modernization Phase 4: Courtyard Project.
On March 7, 2018, the District received contractor bids for the Graham Middle School Modernization Phase 4: Courtyard Project. One (1) bid was received and the apparent low responsive and responsible bidder is Dryco Construction, Inc. The District’s Measure G Bond Program manager, Greystone West, has reviewed the bid for conformance with District and statutory requirements.
Fiscal Implication:
The contract amount will be $535,000.00 with all costs to be charged to the Measure G bond program.
Recommended Action:
That the Board of Trustees award the construction contract for the Graham Middle School Modernization Phase 4: Courtyard Project to Dryco Construction, Inc. in the amount of $535,000.00.
|