Agenda Item Title:  Stevenson Elementary School Phase 2 – Increment 1 Sitework Project - Change Order No. 1 – Galeb Paving, Inc.

Estimated Time: 

Person Responsible:  Dr. Robert Clark, Chief Business Officer



Background: 

During the Stevenson Elementary School Phase 2 – Increment 1 Sitework Project, unforeseen conditions, design changes, and owner requests have occurred, resulting in additions/changes in scope to the original project. These additions/changes require contingency money to be used. Change Order No. 1 will not exceed $246,208.  A summary of Change Order No. 1 is attached.

 

The total construction contingency of $370,200 was budgeted for this project. 



Fiscal Implication:

A total construction contingency of $370,200 is budgeted for this project.

 

Change Order No. 1 for $246,208 results in a remaining contingency balance of $123,992. To date, 30% of the project is complete.

 



Recommended Action: 

That the Board of Trustees approve Change Order No. 1, for the Stevenson Elementary School Phase 2 – Increment 1 Sitework Project.