Item Coversheet

Mountain View Whisman School District

Agenda Item for Board Meeting of 1/18/2018



Agenda Category:  CONSENT AGENDA

Agenda Item Title:  Mariano Castro Elementary School and Gabriela Mistral Elementary School Phase 2 – New Construction Project - Change Order No. 3 – BHM Construction

Estimated Time: 

Person Responsible:  Dr. Robert Clark, Associate Superintendent/Chief Business Officer



Background: 

During the Mariano Castro Elementary School and Gabriela Mistral Elementary School Phase 2 New Construction Project, unforeseen conditions, design changes, and owner requests have occurred, resulting in additions/changes in scope to the original project. These additions/changes require contingency money to be used. Change Order No. 3 will not exceed $101,382.  A summary of Change Order No. 3 is attached.



Fiscal Implication:

A total construction contingency of $2,392,400 is budgeted for this project.

 

Change Order No. 3 for $101,382 results in a remaining contingency balance of $2,392,400. To date, 65% of the project is complete.

 



Recommended Action: 
That the Board of Trustees approve Change Order No. 3, for the Mariano Castro Elementary School and Gabriela Mistral Elementary School Phase 2 New Construction Project.

ATTACHMENTS:
DescriptionTypeUpload Date
Castro Phase 2 - New Construction - Change Order 3Backup Material1/10/2018