Mountain View Whisman School District
Agenda Item for Board Meeting of 8/21/2025
Agenda Category: CONSENT AGENDA
Agenda Item Title: Change Order No. 3- Mountain View Whisman School District Phase 4-5 HVAC Project, EF Brett & Company
Estimated Time:
Person Responsible: Rebecca Westover, Ed.D., Chief Business Officer
Background:
During the Phase 4-5 HVAC Project, unforeseen conditions took place resulting in Change Order No. 3. These changes require contingency money to be used. A construction contingency of $564,000 has been budgeted for this project. Change Order No. 3 for $83,099 will increase EF Brett & Company's contract amount to $4,476,831.
Fiscal Implication:
The monies required for Change Order No. 3 will not exceed $83,099.
Recommended Action:
It is recommended that the Board of Trustees approve Change Order No. 3 for EF Brett & Company for the Phase 4-5 HVAC Project.
|