Background:
During the Community Restroom Project at Castro/Mistral, Imai and Landels, unforeseen conditions occurred which required contingency funds to be used.
The total design contingency or $84,100 was budgeted for this project.
Change Order #1 for $72,225 increased the Public Restroom Company contract amount to $535,689.00
Change Order #2 for $1,835 increased the Public Restroom Company contract amount to $537,524.00
Change Order #3 for $139,605 will increase the Public Restroom Company contract amount to $677,129.00
There is $0 remaining in the design contingency after Change Order No. 3. Additional funds from the overall Measure T program contingency will be used to cover the additional cost.
Fiscal Implication:
The monies required for Change Order #3 will not exceed $139,605.00. This contract is charged to Measure T.
Recommended Action:
It is recommended that the Board of Trustees approve Change Order #3 for the Mountain View Whisman School District Community Restrooms Project.