Mountain View Whisman School District
Agenda Item for Board Meeting of 5/30/2024
Agenda Category: CONSENT AGENDA
Agenda Item Title: Change Order No. 3: District Wide Security Systems Upgrades (Access Control) Project, Paladin Technologies
Estimated Time:
Person Responsible: Rebecca Westover, Ed.D., Chief Business Officer
Background:
During the MVWSD Access Control Project, unforeseen conditions and design revisions have occurred, resulting in revisions to the scope of the original project. These additions/changes require contingency money to be used. A construction contingency of $498,559.99 has been budgeted for this project.
Change Order No. 3 for $56,384.20 will increase the Paladin Technologies contract amount to $5,140,592.85.
Fiscal Implication:
The monies required for Change Order No. 3 will not exceed $56,384.20. After Change Order No. 3, the balance remaining in the construction contingency will be $343,556.14.
Recommended Action:
It is recommended that the Board of Trustees approve Change Order No. 3 for the MVWSD Access Control Project.
|