Agenda Item Title: Change Order No.1: MVWSD HVAC Replacement Phase 3 Project
Estimated Time:
Person Responsible: Rebecca Westover, Ed.D., Chief Business Officer
Background:
The bid documents for the MVWSD HVAC Replacement Phase 3 Project included $50,000 in allowances to account for unforeseen conditions and/or the need for temporary HVAC units during construction. During the course of the project no allowance monies were utilized and will be credited back to the District.
Change Order No. 1 for ($50,000.00) will decrease the Foothill HVAC contract amount to $262,000.00.
Fiscal Implication:
This contract is charged to Measure T.
Recommended Action:
It is recommended that the Board of Trustees approve Change Order No. 1 for the MVWSD HVAC Replacement Phase 3 Project, as presented.
|