During the staff housing project, unforeseen conditions, jurisdictional requirements, and owner-requested changes have resulted in the use of the Owners' Contingency for this project and the project is now at the point where the Developers’ Contingency is being used to fund these additional changes. Change Order No. 10 will decrease the District's contract with Palisade Builders by $492,501.81.

Change Orders No. 1 and No. 2 for this project were no cost contingency adjustments.

Change Order No. 3 for $283,852 increased the contract amount to $68,071,138.55.

Change Orders No. 4, No. 5, and No. 6 for this project were no cost contingency adjustments. Change Order No. 7 for $131,762.79 increased the contract amount to $68,202,901.34. Change Order No. 8 for $215,606.99 increased the contract amount to $68,418,508.33.

Change Order No. 9 for this project was a no-cost contingency adjustment.

Change Order No. 10 for ($492,501.81) will decrease the contract amount to $67,926,006.52.



Fiscal Implication:

None. This contract is charged to Measure T.



Recommended Action: 

It is recommended that the Board of Trustees approve Change Order No. 10 for Palisade Builders for the Staff Housing Project.

ATTACHMENTS:
DescriptionTypeUpload Date
Change Order No. 10- Mountain View Whisman School District Staff Housing Project, Palisade BuildersBackup Material1/31/2024