Agenda Item for Board Meeting of 3/2/2023



Agenda Category:  CONSENT AGENDA

Agenda Item Title:  HVAC Modernization and Replacement Phase 2 Project- BRCO Constructors, Inc.- Change Order No. 2

Estimated Time: 

Person Responsible:  Rebecca Westover, Ed.D., Chief Business Officer



Background: 

During the HVAC Modernization and Replacement Phase 2 project, unforeseen conditions and design revisions have occurred, resulting in revisions to the scope of the original project. These additions/changes require contingency money to be used. A construction contingency of $433,900 has been budgeted for this project. 

Change Order No. 1 for $101,854.00 increased the BRCO Constructors, Inc. contract amount to $4,440,854.00. 

Change Order No. 2 for $13,807.00 will increase the BRCO Constructors, Inc. contract amount to $4,454,66100.



Fiscal Implication:

The monies required for Change Order No. 2 will not exceed $13,807. After Change Order No. 2, the balance remaining in the construction contingency will be $318,239.



Recommended Action: 
It is recommended that the Board of Trustees approve Change Order No. 2 for the HVAC Modernization and Replacement Phase 2 Project.