Mountain View Whisman School District
Agenda Item for Board Meeting of 2/10/2022
Agenda Category: CONSENT AGENDA
Agenda Item Title: Gabriela Mistral Elementary School Phase 4 Increment 3 Administration Building Modernization, Change Order No. 2
Estimated Time:
Person Responsible: Rebecca Westover, Ed.D., Chief Business Officer
Background:
During the Gabriela Mistral Elementary School Administration Building Modernization, unforeseen conditions, design revisions and owner changes have occurred, resulting in revisions in scope to the original project. These additions/changes require contingency money to be used.
The total construction contingency of $216,300 was budgeted for this project.
Change Order No. 1 for $187,850.33 increased the contract amount to $2,350,850.33.
Change Order No. 2 for ($7,681.79) will decrease the contract amount to $2,343,168.54.
Fiscal Implication:
The contingency monies required for Change Order No. 2 will not exceed ($7,681.79). A summary of Change Order No. 2 is attached. There is $36,131.46 remaining in the Change Order Contingency for this project.
Recommended Action:
It is recommended that the Board of Trustees approve Change Order No. 2 for the Gabriela Mistral Elementary School Administration Building Modernization.
|