Agenda Item Title: Mountain View Whisman School District Fencing Upgrades Project Phase 1, Change Order No. 1
Estimated Time:
Person Responsible: Rebecca Westover, Ed.D., Chief Business Officer
Background:
During Phase 1 of the District Wide Fencing Upgrades Project , unforeseen conditions, design revisions and owner changes have occurred, resulting in revisions in scope to the original project. These additions/changes require contingency money to be used.
The total construction contingency of $86,891.90 was budgeted for this project.
Change Order No. 1 for $85,591.37 increased the contract amount to $954,510.37.
Fiscal Implication:
The contingency monies required for Change Order No. 1 will not exceed $85,591.37. A summary of Change Order No. 1 is attached. There is $1,300.53 remaining in the Change Order Contingency for this project.
Recommended Action:
It is recommended that the Board of Trustees approve Change Order No. 1 for the Mountain View Whisman School District Wide Fencing Upgrades Project Phase 1.
|