Item Coversheet

Mountain View Whisman School District

Agenda Item for Board Meeting of 2/10/2022



Agenda Category:  CONSENT AGENDA

Agenda Item Title:  Mountain View Whisman School District Fencing Upgrades Project Phase 1, Change Order No. 1

Estimated Time: 

Person Responsible: 

Rebecca Westover, Ed.D., Chief Business Officer




Background: 

During Phase 1 of the District Wide Fencing Upgrades Project , unforeseen conditions, design revisions and owner changes have occurred, resulting in revisions in scope to the original project. These additions/changes require contingency money to be used.

 The total construction contingency of $86,891.90 was budgeted for this project.

Change Order No. 1 for $85,591.37 increased the contract amount to $954,510.37.



Fiscal Implication:

The contingency monies required for Change Order No. 1 will not exceed $85,591.37. A summary of Change Order No. 1 is attached. There is $1,300.53 remaining in the Change Order Contingency for this project.



Recommended Action: 

It is recommended that the Board of Trustees approve Change Order No. 1 for the Mountain View Whisman School District Wide Fencing Upgrades Project Phase 1.

ATTACHMENTS:
DescriptionTypeUpload Date
Change Order No. 1- MVWSD Fencing Upgrades Project Phase 1Backup Material2/3/2022