Item Coversheet

Mountain View Whisman School District

Agenda Item for Board Meeting of 11/18/2021



Agenda Category:  CONSENT AGENDA

Agenda Item Title:  Mountain View Whisman School District HVAC Modernization and Replacement Project Change Order No. 2, Foothill Air Conditioning and Heating, Inc.

Estimated Time: 

Person Responsible: 

Rebecca Westover, Ed.D., Chief Business Officer




Background: 

During the Mountain View Whisman School District HVAC Modernization and Replacement Project an owner request occurred, resulting in revisions in scope to the original project. These changes require contingency money to be credited back to the District.

The total construction contingency of $485,576 was budgeted for this project.

Change Order No. 2 for ($94,831.00) will credit the contract amount.



Fiscal Implication:

The contingency monies required for Change Order No. 2 are credited back $94,831. The net change to the contract for Change Orders No. 1 & 2 is a credit back to MVWSD for $86,037.



Recommended Action: 

It is recommended that the Board of Trustees approve Change Order No. 2 for the Mountain View Whisman School District HVAC Modernization and Replacement Project.

ATTACHMENTS:
DescriptionTypeUpload Date
Mountain View Whisman School District HVAC Modernization & Replacement Project Change Order No. 2Backup Material11/5/2021