Item Coversheet

Mountain View Whisman School District

Agenda Item for Board Meeting of 10/21/2021



Agenda Category:  CONSENT AGENDA

Agenda Item Title:  Crittenden Middle School & Vargas Elementary Marquee Project - Change Order No. 2, Escon Builders

Estimated Time: 

Person Responsible: 

Rebecca Westover, Ed.D., Chief Business Officer




Background: 

During the Crittenden Middle School & Vargas Elementary Marquee Project, unforeseen conditions have occurred, resulting in revisions in scope to the original project. These additions/changes require contingency money to be used. The total construction contingency of $19,600 was budgeted for this project. 


Change Order #1 for $7,885.01 was approved on October 7, 2021 and increased the contract amount to $203,885.01. 

Change Order #2 for $3,140.79 will increase the contract amount to $207,025.80.



Fiscal Implication:

The contingency monies required for Change Order #2 will not exceed $3,140.79and will increase the contract amount to $207,025.80. A summary of Change Order #2 is attached.



Recommended Action: 

It is recommended the Board of Trustees approve Change Order #2 for the Crittenden Middle School & Vargas Elementary Marquee Project.

ATTACHMENTS:
DescriptionTypeUpload Date
Crittenden Middle School & Vargas Elementary Marquee Project - Change Order No. 2, Escon BuildersBackup Material10/13/2021