Item Coversheet

Mountain View Whisman School District

Agenda Item for Board Meeting of 10/7/2021



Agenda Category:  CONSENT AGENDA

Agenda Item Title:  Solar Photovoltaic System and Data Acquisition System at School Sites Change Order No. 4 - ENGIE Services U.S., Inc.

Estimated Time: 

Person Responsible: 

Rebecca Westover, Ed.D., Chief Business Officer




Background: 

During the District-Wide Solar Photovoltaic System project, unforeseen conditions, design changes and owner requests have occurred, resulting in revisions to the scope of the original project. These additions/changes require contingency money to be used. 

 A design contingency of $886,462 has been budgeted for this project. 
 
Change Order #1 for $305,880.40 increased the Engie Services contract amount to $9,170,496.40. 
Change Order #2 for $445,189.00 increased the Engie Services contract amount to $9,678,301.00. 
Change Order #3 for $33,672.00 will increase the Engie Services contract amount to $9,711,973.00. 
Change Order #4 for $17,480.00 will increase the Engie Services contract amount to $9,666,838.00.


Fiscal Implication:

The monies required for Change Order #4 will not exceed $17,480.00. After Change Order #4, the balance of the design contingency will be $101,670, and the balance remaining in the construction contingency will be $868,932. 



Recommended Action: 

It is recommended that the Board of Trustees approve Change Order #4 for the Solar Photovoltaic System and Data Acquisition System at School Sites Project.

ATTACHMENTS:
DescriptionTypeUpload Date
Amendment No. 4 - Engie Services U.S., Inc. Contract Backup Material9/30/2021
Change Order No. 4 - Solar Photovoltaic System and Data Acquisition System at School Sites - ENGIE Services U.S., Inc.Backup Material9/29/2021