Item Coversheet

Mountain View Whisman School District

Agenda Item for Board Meeting of 9/9/2021



Agenda Category:  CONSENT AGENDA

Agenda Item Title:  Gabriela Mistral Elementary School Administration Building Modernization - Change Order No. 1 S & H Construction

Estimated Time: 

Person Responsible:  Rebecca Westover, Ed. D., Chief Business Officer



Background: 

During the Gabriella Mistral Elementary School Administration Building Modernization, unforeseen conditions, design revisions and owner changes have occurred, resulting in revisions in scope to the original project. These additions/changes require contingency money to be used.

 

The total construction contingency of $216,300 was budgeted for this project.

 

Change Order #1 for $187,850.33 will increase the contract amount.



Fiscal Implication:
The contingency monies required for Change Order #1 will not exceed $187,850.33. A summary of Change Order #1 is attached. There is $28,449.67 remaining in the Change Order Contingency for this project.

Recommended Action: 
It is recommended the Board of Trustees approve Change Order #1 for the Gabriela Mistral Elementary School Administration Building Modernization. 

ATTACHMENTS:
DescriptionTypeUpload Date
Mistral Modernization Project Phase 4 Increment 3 - Change Order No. 1 - S & H Construction Backup Material9/1/2021