Mountain View Whisman School District

Agenda Item for Board Meeting of 9/9/2021



Agenda Category:  CONSENT AGENDA

Agenda Item Title:  Mariano Castro Elementary and Theuerkauf Elementary School Paving Project - Change Order No. 1 - Silicon Valley Paving, Inc.

Estimated Time: 

Person Responsible:  Rebecca Westover, Ed. D., Chief Business Officer



Background: 

During the Mariano Castro Elementary and Theuerkauf Elementary School Paving Project, unforeseen conditions have occurred, resulting in revisions in scope to the original project. These additions/changes require contingency money to be used.

The total construction contingency of $45,000 was budgeted for this project. Change Order #1 for $33,334 will credit the contract amount.



Fiscal Implication:
The contingency monies required for Change Order #1 will not exceed $33,334. A summary of Change Order #1 is attached.

Recommended Action: 
It is recommended the Board of Trustees approve Change Order #1 for the Mariano Castro Elementary and Theuerkauf Elementary School Paving Project.