Background:
During the District-Wide Solar Photovoltaic System project, unforeseen conditions, design changes and owner requests have occurred, resulting in revisions in scope to the original project. These additions/changes require contingency money to be used.
A design contingency of $886,462 has been budgeted for this project.
Change Order #1 for $305,880.40 increased the Engie Services contract amount to $9,170,496.40.
Change Order #2 for $445,189 will increase the Engie Services contract amount to $9,678,301.00.
Fiscal Implication:
The monies required for Change Order #2 will not exceed $445,189. After change order 2, the balance of the design contingency will be $135,392.60, as well as another $886,462 remaining in the construction contingency