Item Coversheet

Mountain View Whisman School District

Agenda Item for Board Meeting of 5/6/2021



Agenda Category:  CONSENT AGENDA

Agenda Item Title:  Solar Photovoltaic System and Data Acquisition System at School Sites Change Order No. 2 – ENGIE Services U.S., Inc.

Estimated Time: 

Person Responsible:  Rebecca Westover, Ed. D., Chief Business Officer



Background: 

During the District-Wide Solar Photovoltaic System project, unforeseen conditions, design changes and owner requests have occurred, resulting in revisions in scope to the original project. These additions/changes require contingency money to be used. 

A design contingency of $886,462 has been budgeted for this project.

Change Order #1 for $305,880.40 increased the Engie Services contract amount to $9,170,496.40.
Change Order #2 for $445,189 will increase the Engie Services contract amount to $9,678,301.00.



Fiscal Implication:

The monies required for Change Order #2 will not exceed $445,189.   After change order 2, the balance of the design contingency will be $135,392.60, as well as another $886,462 remaining in the construction contingency



Recommended Action: 

It is recommended the Board of Trustees approve Change Order #2 for the Solar Photovoltaic System and Data Acquisition System at School Sites Project.  

ATTACHMENTS:
DescriptionTypeUpload Date
Solar Project - Change Order No. 2 ENGIE Services U.S., Inc.Backup Material4/28/2021
Engie Services U.S., Inc.- Second Amendment Solar ContractBackup Material4/28/2021