Agenda Item Title: District-Wide Campus Perimeter Controls Project Phase 2 - Change Order No. 1 – Golden Bay Fence plus Iron Works, Inc.
Estimated Time:
Person Responsible: Rebecca Westover, Ed. D., Chief Business Officer
Background:
During the District-Wide Campus Perimeter Controls Upgrades Project, unforeseen conditions, design changes, and owner requests have occurred, resulting in revisions in scope to the original project. These additions/changes require contingency money to be used.
The total construction contingency of $26,984 was budgeted for this project.
Change Order #1 for $(131,525.00) will credit the contract amount.
Fiscal Implication: The contingency monies required for Change Order #1 will not exceed ($131,525.00.) A summary of Change Order #1 is attached
Recommended Action: It is recommended the Board of Trustees approve Change Order #1 for the District-Wide Campus Perimeter Controls Upgrades Project Phase 2.
|