Item Coversheet

Mountain View Whisman School District

Agenda Item for Board Meeting of 3/4/2021



Agenda Category:  REVIEW AND ACTION

Agenda Item Title:  Schematic Design Drawings, Budget, and Schedule for Vargas Carport (30 minutes)

Estimated Time: 

Person Responsible:  Rebecca Westover Ed. D., Chief Business Officer



Background: 

The District has developed schematic designs for the Vargas Carport Project.

The project includes the installation of a new 4,500 sf steel shade structure, including LED lighting on the underside to illuminate the parking area.

Construction is scheduled for October 2021 through January 2022.

The anticipated total project cost is $542,051. Funding for the Vargas Carport Project is from the Measure T Bond Program.

 



Fiscal Implication:

Measure T Bond Program - $542,051.



Recommended Action: 
It is recommended the Board of Trustees approve the schematic design, budget and schedule presented for the Vargas Carport Project.

ATTACHMENTS:
DescriptionTypeUpload Date
Vargas Carport Presentation Backup Material2/24/2021