Item Coversheet

Mountain View Whisman School District

Agenda Item for Board Meeting of 1/21/2021



Agenda Category:  REVIEW AND ACTION

Agenda Item Title:  Schematic Design Review Huff Elementary School Portable Project (10 minutes)

Estimated Time: 

Person Responsible:  Rebecca Westover Ed.D., Chief Business Officer 



Background: 

The District has developed schematic designs for the Huff Elementary School Portable Classroom Project.

In order to stay on target for construction in the summer of 2021, this project needs to be submitted to the Division of State Architect for Over-the-Counter Review by March 2021. Overall construction is anticipated to take two months from June through August 2021.

The anticipated project cost is $423,379.00. Funding for the Huff Elementary School Portable Project is from the Measure T Bond Program.

 



Fiscal Implication:

Measure T Bond Program - $423,379.00.



Recommended Action: 

 It is recommended the Board of Trustees approve the schematic design, budget and schedule presented for Huff Elementary School Portable Project as presented.

ATTACHMENTS:
DescriptionTypeUpload Date
Huff Portable Location Presentation - Budget & ScheduleBackup Material1/13/2021