Background: 

During the Slater Elementary School MUR, Increment 3 Project, unforeseen conditions, design changes, and owner requests have occurred, resulting in additions/changes in scope to the original project. These additions/changes require contingency money to be used.

The total construction contingency of $199,889 was budgeted for this project.

Change Order #1 for $134,194 was approved on May 2, 2019.

Change Order #2 $35,390 was approved on August 22, 2019.

Change Order #3 for $25,302 will reduce the remaining contingency amount to $5,003.00 with 100% of the project complete.

 



Fiscal Implication:

The contingency monies required for Change Order #3 will not exceed $25,302. A summary of Change Order #3 is attached.



Recommended Action: 
It is recommended the Board of Trustees approve Change Order #3 for the Slater Elementary School MUR, Increment 3 Project.