Agenda Category:  CONSENT AGENDA

Agenda Item Title:  Slater Elementary School Increment 4 Project Change Order No. 2 – Rodan Builders, Inc.

Estimated Time: 

Person Responsible: 

Rebecca Westover, Ed.D., Chief Business Officer




Background: 

During the Slater Elementary School Increment 4 Project, unforeseen conditions, design changes, and owner requests have occurred, resulting in additions/changes in scope to the original project. These additions/changes require contingency money to be used.

The total construction contingency of $202,346 was budgeted for this project.

Change Order #1 for $86,647 was approved on August 22, 2019.

Change Order #2 for $115,426.22 will reduce the remaining contingency amount to $272.78 with 100% of the project complete.

 



Fiscal Implication:

The contingency monies required for Change Order #2 will not exceed $115,426.22. A summary of Change Order #2 is attached.



Recommended Action: 
It is recommended the Board of Trustees approve Change Order #2 for the Slater Elementary School Increment 4 Project.