Item Coversheet

Mountain View Whisman School District

Agenda Item for Board Meeting of 9/3/2020



Agenda Category:  CONSENT AGENDA

Agenda Item Title:  District Office Site - Monument Signage Project Change Order No. 3

Estimated Time: 

Person Responsible:  Rebecca Westover, Ed.D., Chief Business Officer



Background: 

During the MVWSD Site Monument Signage Project unforeseen conditions, design changes, and owner requests have occurred, resulting in additions/changes in scope to the original project. These additions/changes require contingency money to be used.

The total construction contingency of $33,150 was budgeted for this project.

Change Order #1 for $75,499.64 was approved on August 23, 2019.

Change Order #2 for $(4,768.78) was approved on May 21, 2020.

Change Order #3 for $9,152.00 will leave the remaining contingency amount at $0.00 with 100% of the project complete.

 



Fiscal Implication:

The contingency monies required for Change Order #3 will not exceed $9,152.00. A summary of Change Order #3 is attached.

 



Recommended Action: 
It is recommended that the Board of Trustees approve Change Order #3 for the MVWSD Site Monument Signage Project.