Agenda Category:  CONSENT AGENDA

Agenda Item Title:  Landels Play Structure Grant Project - Terramark Change Order No. 2

Estimated Time: 

Person Responsible:   Rebecca Westover, Ed.D., Chief Business Officer



Background: 

During the Landels Play Structure Grant Project unforeseen conditions, design changes, and owner requests have occurred, resulting in additions/changes in scope to the original project. These additions/changes require contingency money to be used.

The total construction contingency of $47,440.00 was budgeted for this project.

Change Order #1 for $25,426.71 was approved on May 21, 2020.

Change Order #2 for $21,525.00 will leave the remaining contingency amount at $488.29 with 100% of the project complete.

 



Fiscal Implication:

The contingency monies required for Change Order #2 will not exceed $21,525.00. A summary of Change Order #2 is attached.

 



Recommended Action: 
It is recommended the Board of Trustees approve Change Order #2 for the Landels Play Structure Grant Project .