Agenda Item Title: Stevenson Park Interface Project - Scapes Inc. Change Order No. 1
Estimated Time:
Person Responsible: Rebecca Westover, Ed.D., Chief Business Officer
Background:
During the Stevenson Park Interface Project unforeseen conditions, design changes, and owner requests have occurred, resulting in additions/changes in scope to the original project. These additions/changes require contingency money to be used.
The total construction contingency of $16,400.00 was budgeted for this project.
Change Order #1 for $4,539.25 will leave the remaining contingency amount at $11,860.75 with 100% of the project complete.
Fiscal Implication:
The contingency monies required for Change Order #1 will not exceed $4,539.25. A summary of Change Order #1 is attached.
Recommended Action: It is recommended the Board of Trustees approve Change Order #1 for the Stevenson Park Interface Project.
|