Background:
During the Theuerkauf Elementary School Multi-Use Room Increment 2 Project, unforeseen conditions, design changes, and owner requests have occurred, resulting in additions/changes in scope to the original project. These additions/changes require contingency money to be used.
The total construction contingency of $290,765 was budgeted for this project.
Change Order #1 for $217,622 was approved on September 19, 2019.
Change Order #2 for $255,611 will decrease the remaining contingency amount to $(182,468) with 100% of the project complete.
Fiscal Implication:
The contingency monies required for Change Order #2 will not exceed $255,611. A summary of Change Order #2 is attached.
Recommended Action:
That the Board of Trustees approve Change Order #2 for the Theuerkauf Elementary School Multi-Use Room Increment 2 Project.
|