Background:
During the Mountain View Whisman School District Office New Construction Project unforeseen conditions, design changes, and owner requests have occurred, resulting in additions/changes in scope to the original project. These additions/changes require contingency money to be used.
The total construction contingency of $182,920 was budgeted for this project.
Change Order #1 for $235,674 was approved on January 24, 2019.
Change Order #2 for $91,224 was approved on April 4, 2019.
Change Order #3 for $63,261 was approved on May 30, 2019.
Change Order #4 for $34,052 was approved on August 22, 2019.
Change Order #5 for $32,048 was approved on October 10, 2019.
Change Order #6 for $21,952 is the last change order on this contract with 100% of the project complete. There is $0.00 remaining in the Change Order Contingency.
Total Change Orders to date equals $478,211.00 which includes the $235,674.00 for unforeseen soils conditions issued as a futile and unavailing change order comprising change order no. 1.
Excluding the unforeseen soils cost, change orders to date equate to 13.32% of the contract value. To date, Premier Builders has completed 100% of the contract work.
Fiscal Implication:
The contingency monies required for Change Order #6 will not exceed $21,952. A summary of Change Order #6 is attached.
Recommended Action:
That the Board of Trustees approve Change Order #6 for the Mountain View Whisman School District Office New Construction Project.