Background:
During the MVWSD Portable Refresh Project unforeseen conditions, design changes, and owner requests have occurred, resulting in additions/changes in scope to the original project. These additions/changes require contingency money to be used.
The total construction contingency of $203,400 was budgeted for this project.
Change Order #1 for $152,982.16 was approved on August 22, 2019.
Change Order #2 for $35,515 will reduce the remaining contingency amount to $11,902.84 with 100% of the project complete.
Total Change Orders to date equal $19,497.16 and equate to 9.41% of the contract value. To date BRCO Contractors has completed 100% of the contract work.
Fiscal Implication:
The contingency monies required for Change Order #2 will not exceed $35,515. A summary of Change Order #2 is attached.
Recommended Action:
That the Board of Trustees approve Change Order #2 for the Mountain View Whisman School District Portable Refresh Project.