Item Coversheet

Mountain View Whisman School District

Agenda Item for Board Meeting of 9/19/2019



Agenda Category:  CONSENT AGENDA

Agenda Item Title:  Notice of Completion – Bubb, Huff and Landels Elementary Schools Concrete Landings Project

Estimated Time: 

Person Responsible:  Rebecca Westover, Ed.D., Chief Business Officer



Background: 

On May 2, 2019, the Board approved the construction contract for the Bubb, Huff and Landels Elementary Schools Concrete Landings Project from Measure G funds.  The Board approved the award of the project to Tri-Valley Excavating Co., Inc. in the amount of $245,918.

 

Work on this project is now substantially complete.



Fiscal Implication:

The District currently holds retention in the amount of $12,296, or 5% of the contract value.  After a minimum of thirty-five (35) days after the filing of the Notices of Completion with the County of Santa Clara recorder, the District will release the retention amount provided all remaining close out and punch list items have been completed.



Recommended Action: 

The Board approve the filing of the Notice of Completion for the Bubb, Huff and Landels Elementary Schools Concrete Landings Project.

ATTACHMENTS:
DescriptionTypeUpload Date
NOC-Tri Valley BHL ConcreteBackup Material9/10/2019