Mountain View Whisman School District
Agenda Item for Board Meeting of 9/19/2019
Agenda Category: CONSENT AGENDA
Agenda Item Title: Castro and Stevenson Playground Extension Project Change Order No. 2– Terramark General Engineering Contractors
Estimated Time:
Person Responsible: Rebecca Westover, Ed.D., Chief Business Officer
Background:
During the Castro & Stevenson Playground Extension Project unforeseen conditions, design changes, and owner requests have occurred, resulting in additions/changes in scope to the original project. These additions/changes require contingency money to be used.
The total construction contingency of $21,400 was budgeted for this project.
Change Order #2 for $10,282 will reduce the remaining contingency amount to $7,046 with 100% of the project complete.
Fiscal Implication: The contingency monies required for Change Order #2 will not exceed $10,282. A summary of Change Order #2 is attached.
Recommended Action:
That the Board of Trustees approve Change Order #2 for the Castro & Stevenson Playground Extension Project.
|