Item Coversheet

Mountain View Whisman School District

Agenda Item for Board Meeting of 8/22/2019



Agenda Category:  CONSENT AGENDA

Agenda Item Title:  MVWSD Site Monument Signage Project Change Order No. 1– Pacific Electric

Estimated Time: 

Person Responsible:  Rebecca Westover, Ed.D., Chief Business Officer



Background: 

During the Mountain View Whisman School District Site Monument Signage Project, unforeseen conditions, design changes, and owner requests have occurred, resulting in additions/changes in scope to the original project. These additions/changes require contingency money to be used.

 

The total construction contingency of $33,150 was budgeted for this project.

 

Change Order #1 for $75,499.64 will reduce the remaining contingency amount to ($42,349.64) with 95% of the project complete.

 



Fiscal Implication:

The contingency monies required for Change Order #1 will not exceed $75,499.64. A summary of Change Order #1 is attached.



Recommended Action: 

That the Board of Trustees approve Change Order #1 for the Mountain View Whisman School District Site Monument Signage Project.