Background: 

During the Slater Elementary School Increment 4 Project, unforeseen conditions, design changes, and owner requests have occurred, resulting in additions/changes in scope to the original project. These additions/changes require contingency money to be used.

 

The total construction contingency of $202,346 was budgeted for this project.

 

Change Order #1 for $86,647 will reduce the remaining contingency amount to $115,699 with 44% of the project complete.

 



Fiscal Implication:

The contingency monies required for Change Order #1 will not exceed $86,647. A summary of Change Order #1 is attached.



Recommended Action: 

That the Board of Trustees approve Change Order #1 for the Slater Elementary School Increment 4 Project .

ATTACHMENTS:
DescriptionTypeUpload Date
Slater Incr 4 CO 1Backup Material8/13/2019