Item Coversheet

Mountain View Whisman School District

Agenda Item for Board Meeting of 8/22/2019



Agenda Category:  CONSENT AGENDA

Agenda Item Title:  Kenneth Slater New Campus Project Modular Buildings Change Order No. 3 – Enviroplex, Inc.

Estimated Time: 

Person Responsible:  Rebecca Westover., Ed.D., Chief Business Officer



Background: 

During the Kenneth Slater New Campus Modular Buildings Project, unforeseen conditions, design changes, and owner requests have occurred, resulting in additions/changes in scope to the original project. These additions/changes require contingency money to be used.

 

The total construction contingency of $279,096 was budgeted for this project.

 

Change Order #1 for $42,970 was approved on January 10, 2019.
Change Order #2 for $101,955 was approved on March 7, 2019.

 

Change Order #3 for $14,188 will reduce the remaining contingency amount to $119,983 with 97% of the project complete.

 



Fiscal Implication:

The contingency monies required for Change Order #3 will not exceed $14,188. A summary of Change Order #3 is attached.



Recommended Action: 

That the Board of Trustees approve Change Order #3 for the Kenneth Slater New Campus Project Modular Buildings Project.