Item Coversheet

Mountain View Whisman School District

Agenda Item for Board Meeting of 8/22/2019



Agenda Category:  CONSENT AGENDA

Agenda Item Title:  Slater Elementary School MUR, Increment 3 Project Change Order No. 2 – Rodan Builders, Inc.

Estimated Time: 

Person Responsible:  Rebecca Westover, Ed.D., Chief Business Officer



Background: 

During the Slater Elementary School MUR, Increment 3 Project, unforeseen conditions, design changes, and owner requests have occurred, resulting in additions/changes in scope to the original project. These additions/changes require contingency money to be used.

 

The total construction contingency of $199,889 was budgeted for this project.

 

Change Order #1 for $134,194 was approved on May 2, 2019.

 

Change Order #2 for $35,390 will reduce the remaining contingency amount to $30,305 with 95% of the project complete.

 



Fiscal Implication:

The contingency monies required for Change Order #2 will not exceed $35,390. A summary of Change Order #2 is attached.



Recommended Action: 

That the Board of Trustees approve Change Order #2 for the Slater Elementary School MUR, Increment 3 Project.