Background:
During the Crittenden Middle School Track and Field and Permanente Creek Trail Extension Project, unforeseen conditions, design changes, and owner requests have occurred, resulting in additions/changes in scope to the original project. These additions/changes require contingency money to be used.
The total construction contingency of $553,000 was budgeted for this project.
Change Order #1 for $324,150 was approved on December 7, 2017.
Change Order #2 for $143,241 was approved on October 4, 2018.
Change Order #3 for ($35,000) will increase the remaining contingency amount to $120,609 with 100% of the project complete.
Fiscal Implication:
The contingency monies required for Change Order #3 will not exceed ($35,000). A summary of Change Order #3 is attached.
Recommended Action:
It is recommended the Board of Trustees approve Change Order #3 for the Crittenden Middle School Track and Field and Permanente Creek Trail Extension Project.