Item Coversheet

Mountain View Whisman School District

Agenda Item for Board Meeting of 5/30/2019



Agenda Category:  CONSENT AGENDA

Agenda Item Title:  Mountain View Whisman School District Office New Construction Project Change Order No. 3 – Premier Builders, Inc.

Estimated Time: 

Person Responsible:  Ron Wheelehan, Interim Chief Business Officer



Background: 

During the Mountain View Whisman School District Office New Construction Project unforeseen conditions, design changes, and owner requests have occurred, resulting in additions/changes in scope to the original project. These additions/changes require contingency money to be used.

 

The total construction contingency of $182,920 was budgeted for this project.

 

Change Order #1 for $235,674 was approved on January 24, 2019.

Change Order #2 for $91,224 was approved on April 4, 2019.

 

Change Order #3 for $63,261 will reduce the remaining contingency amount to ($207,239) with 68% of the project complete.

 

Total Change Orders to date equals $390,159.00 which includes the $235,674.00 for unforeseen soils conditions issued as a futile and unavailing change order comprising change order no. 1.

 

Excluding the unforeseen soils cost, change orders to date equate to 8.48% of the contract value. To date, Premier Builders has completed 68% of the contract work.

 



Fiscal Implication:

The contingency monies required for Change Order #3 will not exceed $63,261. A summary of Change Order #3 is attached.



Recommended Action: 

That the Board of Trustees approve Change Order #3 for the Mountain View Whisman School District Office New Construction Project.

ATTACHMENTS:
DescriptionTypeUpload Date
MVWSD Office - Change Order 3 Backup Material5/23/2019