Agenda Category:  CONSENT AGENDA

Agenda Item Title:  Bubb, Huff and Landels New MUR and Temporary Portable Relocation Project Change Order No. 6 – Rodan Builders, Inc.

Estimated Time: 

Person Responsible:  Ron Wheelehan, Interim Chief Business Officer



Background: 

During the Bubb, Huff and Landels New MUR and Temporary Portable Relocation Project, unforeseen conditions, design changes, and owner requests have occurred, resulting in additions/changes in scope to the original project. These additions/changes require contingency money to be used.

 

The total construction contingency of $1,237,305 was budgeted for this project.

 

Change Order #1 for $178,652 was approved on June 15, 2017.

Change Order #2 for $231,712 was approved on September 7, 2017.
Change Order #3 for $92,854 was approved on March 15, 2018.
Change Order #4 for $99,414 was approved on October 4, 2018.
Change Order #5 for $63,890 was approved on January 10, 2019.

 

Change Order #6 will increase the remaining contingency amount to $594,879 with 100% of the project complete.

 



Fiscal Implication:

The contingency monies required for Change Order #6 will not exceed ($24,096. ) A summary of Change Order #6 is attached.



Recommended Action: 

That the Board of Trustees approve Change Order #6 for the Bubb, Huff and Landels New MUR and Temporary Portable Relocation Project.