Agenda Item Title:  Award of Contract to Joseph Murphy Construction for the Crittenden Middle School and Cooper School Re-Roof Replacement Project

Estimated Time: 

Person Responsible: 

Ron Wheelehan, Interim Chief Business Officer




Background: 

The Board will consider for award a contract for the Crittenden Middle School and Cooper School Re-Roof Replacement Project.

 

On April 25, 2019, the District received contractor proposals for the Crittenden Middle School and Cooper School Re-Roof Replacement Project.  Three (3) proposals were received and the apparent low responsive and responsible bidder is Joseph Murphy Construction. The District’s Measure G Bond Program manager, Greystone West, has reviewed the proposal for conformance with District and statutory requirements.



Fiscal Implication:

The contract amount will be $630,575 with all costs to be charged to the Measure G bond program.



Recommended Action: 

That the Board of Trustees award the contract for the Crittenden Middle School and Cooper School Re-Roof Replacement Project to Joseph Murphy Construction in the amount of $630,575 and authorize staff to issue a purchase order for the work.

ATTACHMENTS:
DescriptionTypeUpload Date
J. Murphy Re-Roof Back-UpBackup Material5/6/2019
Letter of Recommendation J. Murphy Backup Material5/6/2019