Background: 

During the Mountain View Whisman School District Office New Construction Project unforeseen conditions, design changes, and owner requests have occurred, resulting in additions/changes in scope to the original project. These additions/changes require contingency money to be used.

 

The total construction contingency of $182,920 was budgeted for this project.

 

Change Order #1 for $235,674 was approved on January 24, 2019.

 

Change Order #2 for $91,224 will reduce the remaining contingency amount to ($143,978) with 52% of the project complete.

 

Total Change Orders to date equals $326,898.00 which includes the $235,674.00 for unforeseen soils conditions issued as a futile and unavailing change order comprising change order no. 1.

 

Excluding the unforeseen soils cost, change orders to date equate to 5.01% of the contract value. To date, Premier Builders has completed 52% of the contract work.

 



Fiscal Implication:

The contingency monies required for Change Order #2 will not exceed $91,224. A summary of Change Order #2 is attached.



Recommended Action: 
That the Board of Trustees approve Change Order #2 for the Mountain View Whisman School District Office New Construction Project.