Item Coversheet

Mountain View Whisman School District

Agenda Item for Board Meeting of 4/4/2019



Agenda Category:  CONSENT AGENDA

Agenda Item Title:  Slater (Vargas) New Campus Increment 1 Project, Change Order No. 1– Rodan Builders, Inc.

Estimated Time: 

Person Responsible:  Ron Wheelehan, Interim Chief Business Officer



Background: 

During the Kenneth Slater New Campus Increment 1 Project, unforeseen conditions, design changes, and owner requests have occurred, resulting in additions/changes in scope to the original project. These additions/changes require contingency money to be used.

 

The total construction contingency of $470,428 was budgeted for this project.

 

Change Order #1 for $316,858 will reduce the remaining contingency amount to $153,570 with 44% of the project complete.

 



Fiscal Implication:

The contingency monies required for Change Order #1 will not exceed $316,858. A summary of Change Order #1 is attached.



Recommended Action: 
That the Board approve Change Order #1 for the Kenneth Slater (Vargas) New Campus Increment 1 Project.

ATTACHMENTS:
DescriptionTypeUpload Date
Slater/Vargas Increment 1 - Change Order 1 - RodanBackup Material3/26/2019