Mountain View Whisman School District
  Agenda Item for Board Meeting of 5/2/2019 
  Agenda Category:  CONSENT AGENDA
  Agenda Item Title:  Slater/Vargas Elementary School MUR, Increment 3 Project Change Order No. 1 – Rodan Builders, Inc.
  Estimated Time:  
  Person Responsible:  Ron Wheelehan, Interim Chief Business Officer
 
 
  Background: 
 During the Slater/Vargas Elementary School MUR, increment 3 Project, unforeseen conditions, design changes, and owner requests have occurred, resulting in additions/changes in scope to the original project. These additions/changes require contingency money to be used. 
  
The total construction contingency of $199,889 was budgeted for this project. 
  
Change Order #1 for $134,194 will reduce the remaining contingency amount to $65,695 with 52% of the project complete. 
  
  Fiscal Implication:
 The contingency monies required for Change Order #1 will not exceed $134,194. A summary of Change Order #1 is attached. 
  Recommended Action: 
 That the Board of Trustees approve Change Order #1 for the Slater Elementary School MUR, Increment 3 Project. 
  |