Item Coversheet

Mountain View Whisman School District

Agenda Item for Board Meeting of 5/2/2019



Agenda Category:  CONSENT AGENDA

Agenda Item Title:  Slater/Vargas Elementary School MUR, Increment 3 Project Change Order No. 1 – Rodan Builders, Inc.

Estimated Time: 

Person Responsible:  Ron Wheelehan, Interim Chief Business Officer



Background: 

During the Slater/Vargas Elementary School MUR, increment 3 Project, unforeseen conditions, design changes, and owner requests have occurred, resulting in additions/changes in scope to the original project. These additions/changes require contingency money to be used.

 

The total construction contingency of $199,889 was budgeted for this project.

 

Change Order #1 for $134,194 will reduce the remaining contingency amount to $65,695 with 52% of the project complete.

 



Fiscal Implication:

The contingency monies required for Change Order #1 will not exceed $134,194. A summary of Change Order #1 is attached.



Recommended Action: 

That the Board of Trustees approve Change Order #1 for the Slater Elementary School MUR, Increment 3 Project.

ATTACHMENTS:
DescriptionTypeUpload Date
Slater MUR Increment 3 - Rodan CO 1Backup Material4/23/2019