Mountain View Whisman School District
Agenda Item for Board Meeting of 3/21/2019
Agenda Category: CONSENT AGENDA
Agenda Item Title: Slater/Vargas New Campus Increment 1 Project, Change Order No. 1– Rodan Builders, Inc.
Estimated Time:
Person Responsible: Ron Wheelehan, Interim Chief Business Officer
Background:
During the Kenneth Slater (Vargas) New Campus Increment 1 Project, unforeseen conditions, design changes, and owner requests have occurred, resulting in additions/changes in scope to the original project. These additions/changes require contingency money to be used.
The total construction contingency of $470,428 was budgeted for this project.
Change Order #1 for $316,858 will reduce the remaining contingency amount to $153,570 with 44% of the project complete.
Fiscal Implication:
The contingency monies required for Change Order #1 will not exceed $316,858. A summary of Change Order #1 is attached.
Recommended Action:
That the Board of Trustees approve Change Order #1 for the Slater/Vargas New Campus Increment 1 Project.
|