Item Coversheet

Mountain View Whisman School District

Agenda Item for Board Meeting of 3/21/2019



Agenda Category:  CONSENT AGENDA

Agenda Item Title:  Slater/Vargas New Campus Increment 1 Project, Change Order No. 1– Rodan Builders, Inc.

Estimated Time: 

Person Responsible:  Ron Wheelehan, Interim Chief Business Officer



Background: 

During the Kenneth Slater (Vargas) New Campus Increment 1 Project, unforeseen conditions, design changes, and owner requests have occurred, resulting in additions/changes in scope to the original project. These additions/changes require contingency money to be used.

 

The total construction contingency of $470,428 was budgeted for this project.

Change Order #1 for $316,858 will reduce the remaining contingency amount to $153,570 with 44% of the project complete.

 



Fiscal Implication:

The contingency monies required for Change Order #1 will not exceed $316,858. A summary of Change Order #1 is attached.



Recommended Action: 

That the Board of Trustees approve Change Order #1 for the Slater/Vargas New Campus Increment 1 Project.

ATTACHMENTS:
DescriptionTypeUpload Date
Slater Inc. 1 Change Order 1Backup Material3/12/2019